Palmillas-Toluca Pipeline

Project details
1
  • Follow-up of CRE and SEMARNAT Resolutions during the construction process.
  • Carrying out the Administrative Technical Supervision (Owner’s Engineer) of the construction of the 127 km gas pipeline.
  • Surface installations and other special works.
  • Interconnection with Pemex.
  • Supply of the main materials for the construction of the gas pipeline.
Date

2002

Location

Toluca, Estado de Mexico

Industry

Energy

Development phases
1
  • Preparation, procedures and obtaining permission from the CRE.
  • General supervision in the construction of the gas pipeline, surface installations and special works, interconnection with Pemex.
  • Release and negotiation of the right of way, with a census of 2,545 affected.
  • Preparation of physical and electronic Data Room.
  • Preparation and processing of the Declaration of Environmental Impact or Risk before SEMARNAT.
  • Elaboration of a Justifying Technical Study of Land Use Change from forestry to industrial.
  • Procedures for special crossings before Federal and state agencies (CNA, CFE, PEMEX, FFCC).